Home/Insights/Crystal Ridge Can Start Dirt. The Plat Is Not Filed.
← Back to Insights

Market Update · 17 min read

Crystal Ridge Can Start Dirt. The Plat Is Not Filed.

Citrus County’s August 18, 2026 applications list cleared Crystal Ridge Phase 1 (234 lots) and Phase 2A (about 213 lots) so infrastructure can commence. Neither final plat has been submitted. This is a start-of-build tape, not a sold street.

Representational late-morning photograph of a scraped inland Florida sandy lot with silt fence and leftover pines — not a listed property
Editorial illustration — not a photograph of a specific property.
Bridge Point Advisors

Citrus County’s development-applications page, last updated August 18, 2026, says Crystal Ridge can start infrastructure. It also says the final plats are not in. Phase 1 — improvement plans IMP2024-00005 — proposes 234 residential lots and 10 tracts at 5859 W Crystal Oaks Drive in Lecanto. Staff approved that file with conditions, “so infrastructure construction can commence.” A final plat “has not yet been submitted.” Phase 2A — IMP2024-00006 — proposes approximately 213 single-family lots adjacent to W. Crystal Oaks Drive and S. Rock Crusher Road, also in Lecanto, inside the already-approved Crystal Ridge Planned Unit Development (CPA/AA/PUD-22-01). That file is approved “so infrastructure construction can commence.” A final plat “has not yet been submitted.”

Those are two sentences on one county list. They are not a model-home weekend, a sold street, or a list-price range. They are the start-of-build tape for a named Lecanto PUD. Monday’s people-and-schools briefing said Citrus added residents while the classroom count did not boom. This page is the dirt file that sits next to that mix: the county will let roads and utilities begin on these two phases. It has not recorded the lots.

It sits next to the August Census/HUD construction tape, last week’s Freddie Mac 6.95% survey, the September 16 FOMC hike, and the July SLOOS credit tape. An improvement-plan approval does not invent a Lecanto payment. It can change what a buyer is comparing a resale ranch against six to eighteen months from now. For process, keep the Lecanto home guide, the Citrus County market overview, the Florida markets page, and the Florida home buying guide in the same reading list.

The two improvement-plan files

The official list is Development Applications Submitted on citruscounty.gov. Joanna Coutu, AICP, is named as Land Development Director at 3600 W. Sovereign Path, Lecanto. The page itself warns that statuses change and that the posted vintage is August 18, 2026.

On that vintage:

  • Crystal Ridge Phase 1 (IMP2024-00005). Applicant on the list: Pigeon-Ardurra LLC. 234 residential lots and 10 tracts at 5859 W Crystal Oaks Drive, Lecanto. “The application was approved with conditions by staff, so infrastructure construction can commence. A final plat application has not yet been submitted.”
  • Crystal Ridge Phase 2A (IMP2024-00006). Applicant on the list: Ardurra Group, on behalf of Crystal Ridge Property Group, LLC. Approximately 213 single-family residential lots, part of the previously approved Crystal Ridge PUD CPA/AA/PUD-22-01, adjacent to W. Crystal Oaks Drive and S. Rock Crusher Road, Lecanto. “The application has been approved so infrastructure construction can commence. A final plat application has not yet been submitted.”

The two files together propose 234 lots plus about 213 more. That is the county’s own arithmetic, not a branded “447-lot community” and not a promise that every proposed lot will be built, platted, or sold. Phase 2A’s count is printed as “approximately 213.” Keep the “approximately.” Phase 1’s 10 tracts are not extra house lots on the sentence the county wrote. Tracts on an improvement plan are commonly stormwater, lift-station, open-space, or right-of-way parcels. The page does not itemize them. This briefing does not invent the list.

Pigeon-Ardurra LLC and Ardurra Group are the names on the applications. Crystal Ridge Property Group, LLC is the Phase 2A client named on the same line. Those are applicant lines. They are not a production homebuilder, an HOA, a CDD, or a sales-office brand. The county page does not print a builder, a fee schedule, or a starting price. Neither does this page.

The PUD number is the older paper. CPA/AA/PUD-22-01 is the comprehensive-plan / atlas / planned-unit-development file the county says Phase 2A already sits inside. An approved PUD is the land-use box. An approved improvement plan is permission to build the roads, drainage, and utilities inside that box. A recorded final plat is the map that creates lots you can deed. Crystal Ridge has the first two on these phases. It does not have the third.

What “infrastructure can commence” actually is

Infrastructure is the dirt work a later house sits on. On a Florida improvement plan that usually means clearing and grading, stormwater ponds, water and sewer (or the dry utilities that will serve them), lift stations, local streets, and the silt fence you can see from the county road before anyone pours a slab. The August 18 list is permission to start that work on these two phases. It is not a certificate of occupancy, a model-home TCO, or a closing date.

Staff “approved with conditions” on Phase 1. Conditions are ordinary. They can be bonds, easements, utility letters, or plan redlines. The county page does not reprint the condition letter. Until you have that letter in hand, treat Phase 1 as cleared to commence — not as “unconditional.” Phase 2A’s sentence is shorter: approved, so infrastructure can commence. Same missing plat on both.

Census/HUD’s August national starts print — CB26-147 — is a different machine. That file put privately owned housing starts at a 1.275 million seasonally adjusted annual rate and completions at 1.128 million. A Citrus improvement plan is not a start in that survey, and it is not one of Citrus QuickFacts’ 2,102 building permits for 2025. A permit is permission to build a unit. A start is a unit that broke ground in the survey month. An improvement plan is the civil package in front of both. Keep the three clocks next to each other. Do not add them.

Representational late-afternoon photograph of an excavated Florida stormwater basin with sandy banks and young sabal palms — not a listed property
A retention basin is infrastructure, not a house. Representational earthwork, not a Crystal Ridge lot or a priced address.

If a grader is on Crystal Oaks Drive next month, that is consistent with the August 18 sentence. If a sales trailer is there next month, that is a different claim and it is not on this page. If someone is quoting a lot premium off a brochure, ask whether the final plat has been submitted — the county’s own vintage still says no.

The plat is the missing paper

A final plat is the map the board (or the clerk, after the required signatures) records. It creates lot numbers, tracts, rights-of-way, and the legal descriptions a title company will later write on a deed. Until that map is submitted, reviewed, and recorded, the 234 lots and the approximately 213 lots are proposed lots on an improvement plan, not parcels you can buy by lot number.

The same August 18 page is careful about plat language elsewhere. Black Diamond Town Center — IMP2024-00001, 3499 W Norvell Bryant Hwy (CR-486) — already has “approval issued and the subdivision is under construction,” and a final plat (FPLT2025-00003) “awaiting revisions from the applicant.” Corta Black Diamond — FPLT2026-00005, seven non-residential lots at 3503 W Norvell Bryant Hwy — is “awaiting a final mylar for recording.” Crystal Ridge is earlier than both of those commercial files on the plat clock. It is later than the files still “under review.”

That order matters for a buyer who is being walked through a dirt field and asked to reserve a homesite. A reservation on an unplatted phase is a contract conversation, not a recorded lot. Ask for the improvement-plan stamp, the condition letter, and the plat number when it exists. On August 18 the plat number did not exist.

Southern Woods Phase V is the other residential file on the same list that has already cleared infrastructure: IMP2023-00005, 74 lots on Woodfield Circle in Homosassa, approved with conditions, plat not submitted. That is a later Sugarmill Woods village, not a new community name, and it is not this Lecanto PUD. Keep it on the county list. Do not merge it into Crystal Ridge.

Lecanto, not Crystal River

Both Crystal Ridge files are addressed in Lecanto. Phase 1 is 5859 W Crystal Oaks Drive. Phase 2A is the Crystal Oaks / Rock Crusher node. That is unincorporated Citrus, not the Crystal River city limit, and it is not Black Diamond Ranch. Black Diamond Ranch is the existing golf-community guide. Crystal Ridge is a PUD improvement-plan file on the county applications list. The names sit in the same Lecanto map. They are not the same product.

Monday’s population-versus-school briefing is the people tape for that map. BEBR’s April 1, 2025 estimate put unincorporated Citrus at 155,292 — almost all of the official county gain. Crystal River’s official April 1 count was 3,271, down 125. Census QuickFacts’ July 1, 2025 county estimate is 171,666. The school district’s January 27, 2025 preliminary projection was 14,845 students. Crystal Ridge is more rooftops in the unincorporated geography where the state already put the people. It is not a classroom-boom story the district printed, and it is not a downtown Crystal River story BEBR printed.

Representational mid-morning photograph of a two-lane inland Florida county road through sand pine and palmetto — not a listed property
A two-lane inland county road. Representational Nature Coast arterial, not a Rock Crusher address and not a listed lot.

Rock Crusher Road is a real county road between the SR-44 / CR-490 country and the Lecanto interior. The county page uses it as a locator, not as a traffic study. This briefing does not invent a trip-generation number, an interchange opening date, or a commute time. What it can say is that the same applications list also carries the county’s own CR-486 Interchange Management Area file — CPA-2025-00008 — with an adoption hearing set for October 26, 2026, at 5:01 p.m. That is a comprehensive-plan map around the Suncoast / Norvell Bryant node. It is not Crystal Ridge, and it is not a promise that these lots sit inside the IMA.

The already-published Lecanto guide and the Lecanto retail corridor guide are still the place to read the CR-491 / CR-486 commercial habit. Crystal Ridge does not replace them. It adds a named residential PUD on the inland side of that hub, at the stage the county has actually reached: infrastructure may start; lots are not recorded.

The corridor tape next to the dirt tape

Florida’s Turnpike Enterprise and FDOT have a public design tape for the next Suncoast Parkway 2 increment — Phase 3, CR-486 to US-19 in Citrus County. The official virtual public information meeting is the video below. It is a Turnpike/FDOT meeting archive, not a Crystal Ridge sales clip, and not a claim that these lots sit on the parkway right-of-way. It is the corridor file that belongs in the same Lecanto reading stack as CR-486, Rock Crusher, and the county’s October 26 IMA hearing.

Official Florida’s Turnpike Enterprise / FDOT design public information meeting for Suncoast Parkway 2 Phase 3 (CR-486 to US-19). Project archive, not a subdivision advertisement.

The meeting names Phase 3A as CR-486 to CR-495 and Phase 3B as CR-495 to US-19. Phase 1 of Suncoast Parkway 2, on that same presentation, is the already-open segment from US-98 to SR-44 in Lecanto. Use the video for the official alignment story. Use the August 18 applications list for Crystal Ridge. Do not treat a parkway design meeting as a plat.

The same county list that is not starting

The August 18 page is also the list of what not to call a groundbreaking. These files are on the same table. They are entitlements or review. They are not Crystal Ridge, and they are not under construction on the sentences the county wrote:

  • The Hills of Lecanto (IMP2026-00006) — 38 townhome units at 2225 N Pine Cone Ave., Lecanto. Under review.
  • Post Oak Ranch (CPA/AA-PUD-2026-00005) — about 599 acres at 6750 W 7 Rivers Drive, Crystal River; 1,900 single-family, 300 multi-family, 100,000 square feet of general commercial. Sufficiency review. No hearings set.
  • River Oaks (PUD-2026-00002) — Pulte Home Company, LLC; up to 667 units on 267.2 acres at 6450 N Carl G Rose Hwy (SR-200) in Hernando. PDC recommended denial July 2, 2026; BOCC August 25, 2026. This briefing does not invent the board outcome.
  • Trailhead Ridge Phase 1A (PPLT2024-00006 / FPLT2025-00008) — 238 lots at 6906 N Lecanto Hwy, Beverly Hills. Staff has requested more information.
  • Trailhead Ridge Phase 1B (IMP2026-00001) — 209 lots and 3 tracts, same address. Additional information requested.
  • Amber Ridge Phase 1 (IMP2026-00002) — 129 lots at 3869 W Norvell Bryant Hwy, Lecanto. Additional information requested.
  • Bellamere Phase 1 (IMP2026-00005) — 317 lots; Citrus Hills DRI. Under review.
  • Lecanto Preserve Phase 2 (IMP2026-00004) — 245 lots at 3588 W Gulf to Lake Hwy. Awaiting fee payment before review.

Those counts are what the county printed. They are not absorption, and they are not a 2027 delivery schedule. A listing or a land flyer that lumps them with Crystal Ridge as “Lecanto is exploding” is mixing review files with a commence-infrastructure file. Keep the statuses.

Black Diamond Town Center is the commercial contrast on the same page, not a second residential pitch. IMP2024-00001 at 3499 W Norvell Bryant Hwy already says the nonresidential subdivision “is under construction.” That is the one already in the ground. It is also not the Black Diamond Ranch home guide. Ranch is the golf community. Town Center is the CR-486 commercial plat. Crystal Ridge is the inland residential PUD. Three files, three products.

How this sits next to people, schools, and starts

Citrus added people on both official population clocks — 166,500 on BEBR’s April 1, 2025 estimate and 171,666 on Census QuickFacts’ July 1, 2025 estimate — and almost all of the April 1 gain was unincorporated. The school district still projected 14,845 students. QuickFacts’ age mix is 38.1 percent 65-and-over and 14.2 percent under 18. Crystal Ridge’s 234 plus about 213 proposed lots are more unincorporated houses in a county whose official mix is older households, not a kindergarten boom.

That does not make the lots worthless. It tells you who the county has actually been adding, and it tells you a “near the elementary” remark has to get past the district’s own preliminary file. Citrus Added People. The School Count Did Not. is that briefing. This page does not reprint it.

Citrus 2050 is the comprehensive-plan update on citruscounty.gov. The current operating plan is still the 2030 plan. The rewrite runs into winter 2027, with an open house on October 19, 2026, at the Lecanto Government Building. An open house is not a rezoning of Crystal Oaks Drive. An improvement plan is not Citrus 2050. Keep the plan clock and the plat clock separate.

The national construction tape is still Starts Were 1.275 Million. Completions Fell 12%.. Completions fell 11.9 percent in August and that drop cleared Census’s interval. A Lecanto improvement plan that can commence is local permission. It is not a national completion. If these phases pour streets and then sit, they will look like the national finishing-pace story. If they plat and then sell, that will show up later on a plat book and a deed — not on this August 18 list.

What this tape is not

It is not the Black Diamond Ranch home guide, not a Crystal River or Homosassa tour, not a builder, HOA, CDD, or list-price print, and not a Citrus closed-sale median. Those figures are not on the August 18 applications page. Neighborhood files stay neighborhood files. It is also not the 6.95% Freddie Mac survey, not the September 16 FOMC hike, and not the August starts print. Those national tapes change the payment and the construction backdrop. They do not record a plat on Crystal Oaks Drive.

What it does to housing

For a new-construction shopper, treat Crystal Ridge as a named PUD that may now see dirt, not as a street you can close this Saturday. Ask three questions the county page actually supports: Has the improvement plan been stamped (yes, on August 18, Phase 1 with conditions)? Has a final plat been submitted (no, on August 18)? Who is the applicant on the file (Pigeon-Ardurra LLC on Phase 1; Ardurra Group / Crystal Ridge Property Group, LLC on Phase 2A)? Then ask the questions the county page does not answer: who is building the houses, what the payment is after any buydown expires, and whether the lot you are being shown exists on a recorded map. Last week’s 6.95% survey is the rate tape. A written quote dated after September 17 is the payment. If a Florida Housing second is in the stack, use the Hometown Heroes briefing.

For a resale buyer in Lecanto, 234 plus about 213 proposed lots are future competition if they plat and get built — not a key this weekend. Completions nationally fell in August. Citrus still authorized 2,102 units in 2025. A ranch on an existing street is a different product from an unplatted phase. Shop the roof, the insurance, the flood zone, and the monthly payment. The Lecanto guide is the existing-housing file. Citrus Hills, Pine Ridge, Beverly Hills, and Citrus Springs remain the nearby street files. Do not price a 1990s ranch as if Crystal Ridge had already delivered 400 closings.

For a seller near Crystal Oaks Drive or Rock Crusher Road, an improvement-plan approval is a disclosure item, not an automatic markdown and not an automatic raise. Buyers will ask what is coming. The honest answer on the August 18 vintage is: infrastructure may start; the plats are not in. Price against current comps on the same street type. The pricing strategy guide is the process. A quieter school count and a 6.95% survey already sit behind Saturday traffic. A dirt phase that has not been platted does not repair a high ask or an uninsurable roof.

Insurance and flood stay separate. An improvement plan does not reprice an HO-3. Keep the flood and insurance guide next to the Lecanto conversation; the paperwork logic is the same. A pre-approval from July is still a credit story. VantageScore 4.0 does not turn an unplatted lot into a deed.

What it does to commercial real estate

Crystal Ridge is a residential PUD file. The commercial cousin on the same list is already in the ground: Black Diamond Town Center at 3499 W Norvell Bryant Hwy. Pads, clinics, and service bays that want rooftops still have to clear a tenant who can pay and a bank that will do the loan. The July SLOOS briefing said construction and land-development demand weakened even where standards were unchanged. Census and the county count units and lots. SLOOS asks whether the dirt loan still happens. Keep them next to each other.

The Citrus commercial overview, the Lecanto corridor guide, the Citrus medical guide, and Citrus commercial land are the sector files. Do not paste 234 plus 213 onto a CR-486 asking cap. Household formation in the county tape is still small and owner-heavy — 2.24 persons per household and an 85.2 percent owner-occupied share on QuickFacts. That is a grocery, medical, and services county more than a school-driven retail county. A new inland phase can add rooftops to that map. It does not invent a cap rate this week.

Land next to an unplatted phase is still land. Entitlement, utilities, access, and flood decide value. Lease versus buy is the occupancy file. Citrus 2050 and the October 26 CR-486 IMA hearing can change where density and access are allowed. They do not price a vacant acre this afternoon.

How to use this briefing on a specific lot

Print the vintage. If you are talking to a lender, an appraiser, or a seller, say “Citrus County development applications, updated August 18, 2026: Crystal Ridge Phase 1, IMP2024-00005, 234 lots, infrastructure can commence, final plat not submitted.” Do the same for Phase 2A and IMP2024-00006. Do not say “Crystal Ridge is selling.”

Put the plat sentence in the same paragraph as the lot count. 234 lots and about 213 lots without “plat not submitted” is a brochure. The county wrote both halves.

Keep Crystal Ridge, Black Diamond Town Center, and Black Diamond Ranch in three different sentences. One is an inland residential PUD that may now see infrastructure. One is a CR-486 commercial subdivision already under construction. One is an existing golf community with its own home guide.

Price a house against comps and a current quote, not against either improvement-plan file. The ACS owner-value on QuickFacts is $245,500. The rate tape is 6.95% as of the September 17 Freddie Mac survey. The policy tape is 3.75–4.00% after the September 16 hike. None of those three is a Crystal Ridge list price, because the county page does not print one.

If the decision is whether to wait for these lots, use the plat book when it exists and the house that is actually framed. If the decision is city versus unincorporated, use BEBR’s municipal table. If the decision is whether Citrus 2050 or the CR-486 IMA changes the node, use the October 19 open house, the October 26 adoption hearing, and the adopted ordinance when it exists. Statewide context stays on the Florida markets page.

The through-line

Crystal Ridge Phase 1 can start infrastructure on 234 lots and 10 tracts at 5859 W Crystal Oaks Drive. Phase 2A can start infrastructure on about 213 lots at Crystal Oaks and Rock Crusher. Both sentences are on Citrus County’s August 18, 2026 applications list. Both final plats are still out. The people tape next to that dirt is unincorporated, older, and not a school boom. The rate tape is 6.95%. The construction tape is national starts at 1.275 million and completions down 12 percent. If you are buying, listing, or shopping a still-empty field in Lecanto this fall, use the county status, a current quote, and the house or lot that actually exists on paper. Do not use an improvement plan as a recorded plat, a builder name the page did not print, or a sold-street story the clerk has not seen.

Bridge Point’s residential buying and home selling pages are the service layer when you want that read against a specific address.

What to watch next

  • Citrus applications list: the next staff update after August 18, 2026 — watch for a Crystal Ridge final-plat number.
  • Citrus 2050 open house: October 19, 2026, 5:30–7:30 p.m., Lecanto Government Building.
  • CR-486 Interchange Management Area (CPA-2025-00008): adoption hearing October 26, 2026, 5:01 p.m.
  • August new-home sales (national): Census/HUD, September 24. Separate sales tape.
  • Next Freddie Mac PMMS: September 24.
  • Minutes of the September 15–16 FOMC meeting: October 7.

Sources: Citrus County Board of County Commissioners, Development Applications Submitted, page updated August 18, 2026 — Crystal Ridge Phase 1 IMP2024-00005 (234 residential lots and 10 tracts, 5859 W Crystal Oaks Drive, Lecanto; approved with conditions; infrastructure may commence; final plat not submitted); Crystal Ridge Phase 2A IMP2024-00006 (approximately 213 single-family lots; CPA/AA/PUD-22-01; W. Crystal Oaks Dr. / S. Rock Crusher Road, Lecanto; approved; infrastructure may commence; final plat not submitted); Black Diamond Town Center IMP2024-00001 / FPLT2025-00003; Southern Woods Phase V IMP2023-00005; Hills of Lecanto IMP2026-00006; Post Oak Ranch CPA/AA-PUD-2026-00005; River Oaks PUD-2026-00002; Trailhead Ridge, Amber Ridge, Bellamere, and Lecanto Preserve Phase 2 statuses as printed; CPA-2025-00008 CR-486 Interchange Management Area (PDC May 7, 2026 approval; BOCC June 22, 2026 transmit; adoption set October 26, 2026, 5:01 p.m.). Florida’s Turnpike Enterprise / FDOT, Suncoast Parkway 2 Phase 3 virtual public information meeting (CR-486 to US-19), official recording. Census QuickFacts Citrus County (V2025) and BEBR / Florida DEC April 1, 2025 estimates, Citrus County Schools January 27, 2025 projection, and citruscounty.gov Citrus 2050 cited as the already-published people-and-plan tape. Freddie Mac PMMS (September 17, 2026), FOMC statement (September 16, 2026), Census/HUD CB26-147, and the July 2026 SLOOS cited only as separate national tapes.

For help reading this against a specific house, lot, or site in Citrus County — or against Hernando, Pasco, Hillsborough, or Pinellas — contact Bridge Point Business & Real Estate Advisors at 352-515-0226 or request a consultation.

Questions people ask first

Quick answers to common questions about this topic.

What is Crystal Ridge in Lecanto?+

It is a named planned unit development on Citrus County’s development-applications list. Phase 1 (IMP2024-00005) proposes 234 residential lots and 10 tracts at 5859 W Crystal Oaks Drive. Phase 2A (IMP2024-00006) proposes approximately 213 single-family lots at W. Crystal Oaks Drive and S. Rock Crusher Road, inside CPA/AA/PUD-22-01.

Can Crystal Ridge start construction?+

On the August 18, 2026 county list, both improvement-plan files are approved so infrastructure construction can commence. Phase 1 was approved with conditions. That is roads, drainage, and utilities — not a recorded lot and not a finished house.

Has the Crystal Ridge plat been filed?+

No. The county’s August 18, 2026 vintage says a final plat application has not yet been submitted for Phase 1 or Phase 2A. Proposed lot counts are not recorded parcels until a final plat is submitted, approved, and recorded.

How many lots are in Crystal Ridge?+

Phase 1 proposes 234 residential lots and 10 tracts. Phase 2A proposes approximately 213 single-family lots. The county printed those two figures separately. This page does not turn them into a branded community total or a sold-out count.

Who is the builder?+

The county page names applicants, not a production homebuilder. Phase 1 lists Pigeon-Ardurra LLC. Phase 2A lists Ardurra Group on behalf of Crystal Ridge Property Group, LLC. There is no HOA fee, CDD, or list-price range on that page.

Is Crystal Ridge the same as Black Diamond Ranch?+

No. Black Diamond Ranch is an existing Lecanto golf community with its own home guide. Crystal Ridge is a separate inland PUD improvement-plan file. Black Diamond Town Center, also on the August 18 list, is a CR-486 commercial subdivision already under construction.

Is this in Crystal River?+

No. Both files are addressed in Lecanto, unincorporated Citrus County. BEBR’s April 1, 2025 table put almost all of the county’s recent population gain in unincorporated Citrus. Crystal River’s official April 1 count fell.

Does this mean Citrus is in a school-age housing boom?+

No. Citrus County Schools’ January 27, 2025 preliminary projection was 14,845 students. Census QuickFacts lists 38.1% of residents as 65 and over. More proposed lots in Lecanto sit next to that mix. They do not rewrite the school file.

Should I wait to buy a Lecanto resale because Crystal Ridge is coming?+

Waiting on an unplatted phase is not a plan. Infrastructure may start. The plats are not in. Shop the house that clears today’s payment and a current written quote. The national August starts tape and the 6.95% Freddie Mac survey are separate clocks.

What else on the county list is actually under construction?+

Black Diamond Town Center (IMP2024-00001) at 3499 W Norvell Bryant Highway is the file the county itself lists as under construction. Hills of Lecanto, Post Oak Ranch, Trailhead Ridge, Amber Ridge, Bellamere, and Lecanto Preserve Phase 2 are review or entitlement files, not groundbreakings on that page.

What should I watch next on Crystal Ridge?+

A final-plat application number on a later update of the county applications page. Until that number exists, the lots are still proposed. The October 19 Citrus 2050 open house and the October 26 CR-486 IMA hearing are plan clocks, not plat clocks.

Who can help apply this county file to a specific Lecanto property?+

Bridge Point Business & Real Estate Advisors advises buyers and sellers across Citrus, Hernando, Pasco, Hillsborough, and Pinellas. Call 352-515-0226 or request a consultation.

Talk with Bridge Point

Considering a purchase or sale in this market? Local guidance can make a meaningful difference.

Schedule a consultation

More articles

Representational late-morning photograph of a Nature Coast spring-fed creek through unincorporated marsh and cabbage palms — not a listed property

Market Update · 19 min read

Citrus Added People. The School Count Did Not.

Census QuickFacts puts Citrus County at 171,666 people. BEBR’s April 1, 2025 estimate is 166,500. The school district projected 14,845 students for 2025–26. The plan being rewritten is Citrus 2050.

Representational late-morning photograph of unfinished wood house frames on a concrete slab under a bright sky — not a listed property

Market Update · 16 min read

Starts Were 1.275 Million. Completions Fell 12%.

Census/HUD’s August construction release put housing starts at a 1.275 million annual pace. Single-family rebounded to 918,000. Completions fell 11.9% to 1.128 million. The starts move did not clear the error band.

Bridge Point Business & Real Estate Advisors

Real Estate Decisions. Better Advised.

Quick links

  • Commercial
  • Residential
  • Appraisals
  • Mortgage
  • Insights
  • About
  • Contact

Resources

  • Florida markets
  • Communities
  • Market reports
  • Property Management
  • Business Brokerage
  • Title

Connect

352-515-0226

info@BridgePointBREA.com