Black Diamond Town Center Is the One Already in the Ground

Citrus County’s August 18, 2026 applications list says Black Diamond Town Center at 3499 W Norvell Bryant Highway is under construction. Improvement plans IMP2024-00001 are approved. Final plat FPLT2025-00003 is in and awaiting applicant revisions. This is the CR-486 commercial subdivision, not the Black Diamond Ranch home guide.

Representational midday photograph of graded commercial pads, stacked concrete pipe, and a divided highway lined with sabal palms — not a listed property
Editorial illustration — not a photograph of a specific property.
Bridge Point Advisors

Citrus County’s development-applications page, last updated August 18, 2026, says Black Diamond Town Center is already under construction. Improvement plans IMP2024-00001 propose nonresidential lots and infrastructure at 3499 W Norvell Bryant Hwy (CR-486) in Lecanto. The county’s sentence is short: approval has been issued, and the subdivision is under construction. A final plat was submitted — FPLT2025-00003 — and is awaiting revisions from the applicant.

That is the commercial file on the same list that is further along than a start-of-infrastructure approval. It is not a tenant roster, a rent roll, or a cap rate. It is not the Black Diamond Ranch home guide. Ranch is the existing golf community. Town Center is a nonresidential subdivision on County Road 486. The names share two words. They are not the same product.

It sits next to Crystal Ridge, the people-and-schools briefing, the August Census/HUD construction tape, the Freddie Mac 6.95% survey, the September 16 FOMC hike, and the July SLOOS credit tape. An improvement plan that is under construction does not invent a Lecanto rent. It can change what a user, a pad buyer, or a nearby homeowner is looking at on Norvell Bryant Highway. For process, keep the Lecanto retail corridor guide, the Citrus commercial overview, the Lecanto home guide, and the Florida markets page in the same reading list.

The sentence on the August 18 list

The official list is Development Applications Submitted on citruscounty.gov. Joanna Coutu, AICP, is named as Land Development Director at 3600 W. Sovereign Path, Lecanto. The page warns that statuses change and that the posted vintage is August 18, 2026.

On that vintage, the Town Center line is specific, and it is also narrow:

  • Applicant: Pigeon-Ardurra LLC.
  • File: improvement plans IMP2024-00001.
  • What it proposes: nonresidential lots and infrastructure for a nonresidential site.
  • Address: 3499 W Norvell Bryant Hwy (CR-486), Lecanto.
  • Status: approval issued, and the subdivision is under construction.
  • Plat: final plat FPLT2025-00003 submitted, awaiting revisions from the applicant.

The county did not print a lot count. It did not print square footage. It did not print a tenant, a builder, an HOA, a CDD, a rent, or a price. Those fields stay empty on purpose. Nonresidential lots are the product the page named. Turning that phrase into a numbered retail center, a square-footage claim, or a lease-up is a brochure the county did not write.

Pigeon-Ardurra LLC is the applicant on the line. On other files the same page sometimes says a firm is acting on behalf of a named client. The Town Center line does not. Crystal Ridge Phase 2A names Crystal Ridge Property Group, LLC. Corta Black Diamond, next door, names Corta Black Diamond, LLC. Town Center’s applicant line stops at Pigeon-Ardurra LLC. That is an application name. It is not a production builder, a landlord, or a sales office.

What under construction is, and what the open plat still is

An improvement plan is the civil package: grading, stormwater, water and sewer, local streets, and the other infrastructure a later building sits on. Approval issued means staff cleared that package. The subdivision is under construction means the county is not describing a file that is still in review. On this vintage, dirt work is the status, not a future tense.

A final plat is the map that creates lots a deed can name. FPLT2025-00003 exists. It has been submitted. It is not recorded. Awaiting revisions from the applicant means the plat is back with the applicant for changes staff still wants. Until those revisions are made, accepted, and the plat is recorded, the nonresidential lots are proposed lots on an open plat, not parcels a title company can insure by lot number.

Both halves of the sentence belong in the same paragraph. Under construction, without the open plat, sounds like a finished commercial subdivision. An unrecorded plat, without the construction sentence, sounds like Crystal Ridge, which is earlier on the clock. Town Center is the middle case the county actually printed: the subdivision work is underway, and the recordable map is still open.

Representational mid-morning photograph of an open utility trench, gray conduit, and a precast concrete inlet on a sandy Florida commercial site — not a listed property
Conduit and a storm inlet are infrastructure. Representational earthwork, not the 3499 address and not a priced pad.

Citrus County’s non-residential development page says that work includes commercial businesses or structures, houses of worship, multi-family, institutional uses, and site modifications. The path depends on type, location, and the land-use designation. A pre-application conference is how an owner gets the specific path. Land Development is at 3600 W. Sovereign Path, Suite 141, Lecanto, and those conferences are typically held Monday and Tuesday mornings. That process page does not replace the August 18 status line. It explains why an improvement plan and a final plat are different papers inside one commercial subdivision. Engineering plan review and a later building permit are later papers still. An improvement plan is not a certificate of occupancy.

Census and HUD’s August national starts print — CB26-147 — is a third clock. Privately owned housing starts ran at a 1.275 million seasonally adjusted annual rate. Completions ran at 1.128 million, 11.9 percent below the revised July figure, and that drop cleared Census’s interval. A Citrus commercial improvement plan is not a housing start in that survey, and it is not one of QuickFacts’ 2,102 Citrus building permits for 2025. A permit authorizes a unit. A start is a unit that broke ground in the survey month. An improvement plan is the civil package in front of a later building permit. Keep the clocks separate. Do not add a commercial subdivision to the national housing-starts total.

This is not Black Diamond Ranch

Black Diamond Ranch already has a home guide. It is the golf community buyers ask about when they say Black Diamond in Lecanto. Town Center is the commercial subdivision the county addressed at 3499 W Norvell Bryant Highway. The home guide covers houses, club context, and resale. This briefing covers an improvement plan and an open plat. If a flyer uses one name for both, split them before you price anything.

The Lecanto home guide is the residential file for the hub around County Roads 491 and 486. The Lecanto retail corridor guide is the already-published commercial habit of that node, including the retailers that made Lecanto the county’s everyday commercial center. Town Center does not replace either guide. It adds the one named nonresidential subdivision the August 18 list itself calls under construction. The Citrus County market overview stays the residential county file. This page does not rewrite it.

The file next door is further along on the plat

Corta Black Diamond is the adjacent commercial plat. Ardurra Group, on behalf of Corta Black Diamond, LLC, requested final plat FPLT2026-00005. The site proposes seven non-residential lots and one tract at 3503 W Norvell Bryant Hwy (CR-486), Lecanto. Staff has recommended approval. The file is awaiting a final mylar for recording.

That is a different status from Town Center. Corta has a lot count the county printed: seven lots and one tract. Town Center does not. Corta is at the mylar, the signed drawing that gets recorded. The page does not say Corta is under construction. Town Center is the file with that construction sentence, and its plat is still in revisions. Two commercial files, one address apart — 3499 and 3503 — and two clocks. Do not merge them into a single project with a combined lot count. The county did not.

A tract on a plat is commonly stormwater, open space, or a shared parcel. The page does not itemize Corta’s one tract. This briefing does not invent the use. Seven lots plus one tract is the whole official count. It is not a rent roll, and it is not Town Center’s missing lot count.

The rest of Norvell Bryant is still paper

The same August 18 page is full of CR-486 files that are not groundbreakings. Read the verb. If the verb is under review, additional information, sufficiency review, or a tentative hearing, it is not Town Center.

  • Amber Ridge Phase 1 (IMP2026-00002). Pigeon-Ardurra LLC. 129 residential lots at 3869 W Norvell Bryan Hwy — that is the county’s spelling on that line — Lecanto. Additional information has been requested. Not under construction.
  • Sola Vista Villas (IMP2026-00003). Burrell Engineering. 8 residential lots at 1513 W Norvell Bryant Hwy, Lecanto. Under review.
  • Mythri Lecanto (CPA/AA/PUD-2025-00009). Kimley-Horn and Associates and attorney Sid Ansbacher, on behalf of Mythri Lecanto LLC. 8 general-commercial lots and 2 high-density residential lots at 3768 W Norvell Bryant Hwy. The applicants are revising the submittal and have requested a November or December Planning and Development Commission meeting. The date column shows a tentative November 12, 2026. A tentative hearing is not an approval.
  • SN Lecanto 486 (CPA/AA-PUD-2026-00003). NV5, on behalf of SN Lecanto 486 LLC. About 79 acres at 4134 W Norvell Bryant Hwy. The proposal is 300 multifamily units, 230,000 square feet of general commercial, and 130,000 square feet of professional service and office. Additional information has been requested before public hearings can be scheduled. Those square feet are a proposal still short of a hearing. They are not a building under construction, and they are not Town Center’s missing square footage.
  • Damron PUD (CPA/AA/PUD-2026-00004). Local Engineering. About 5 acres at 4290 W Norvell Bryant Hwy. The page places this one in Crystal River, not Lecanto. It proposes a professional and medical office center. Sufficiency review. No hearing date on the August 18 list.
  • YMCA Lecanto. Two building permits at 4127 on the same highway: BLD2606-1325 for four pickleball courts at 4127 W Norvell Bryant, and BLD2606-0765 for a 5,000 square-foot addition and interior renovations. The addition line spells the road Novell. Those are permits on an existing campus. They are not IMP2024-00001.

A corridor flyer that adds 129 lots, 8 villas, 300 apartments, 230,000 square feet, and Town Center into one CR-486 pipeline is mixing review files with the one subdivision the county says is under construction. Keep the statuses. The square feet on the SN Lecanto 486 line are especially easy to borrow. They belong to a comprehensive-plan and PUD request that still needs more information before a hearing. They do not fill in the blank the Town Center line left on purpose.

Representational late-morning photograph of a new concrete curb and an empty asphalt commercial apron with blank survey ribbons — not a listed property
A curb and an apron are how a commercial lot meets the road. Representational frontage, not a storefront and not a listed pad.

Other files on the same August 18 list are entitlements or review, and the county does not call them under construction either. Hills of Lecanto (IMP2026-00006) is 38 townhome units at 2225 N Pine Cone Ave., under review. Post Oak Ranch (CPA/AA-PUD-2026-00005) is about 599 acres at 6750 W 7 Rivers Drive, Crystal River, proposing 1,900 single-family units, 300 multifamily units, and 100,000 square feet of general commercial, still in sufficiency review. River Oaks (PUD-2026-00002), Pulte Home Company, LLC, is up to 667 units on 267.2 acres at 6450 N Carl G Rose Hwy in Hernando. The Planning and Development Commission date is a July 2, 2026 denial. The Board of County Commissioners date is August 25, 2026. This briefing does not invent a board outcome the applications page did not print as an approval. Trailhead Ridge, Bellamere, and Lecanto Preserve Phase 2 are information, review, or fee files. Southern Woods Phase V (IMP2023-00005) is the other residential file cleared so infrastructure can commence: 74 lots on Woodfield Circle in Homosassa, plat not submitted. That is a later Sugarmill Woods village, not a Lecanto commercial subdivision.

Crystal Ridge is the residential contrast

Crystal Ridge is the inland Lecanto planned unit development. Phase 1, IMP2024-00005, is 234 lots and 10 tracts at 5859 W Crystal Oaks Drive, approved with conditions so infrastructure can commence, final plat not submitted. Phase 2A, IMP2024-00006, is about 213 single-family lots at Crystal Oaks and Rock Crusher, the same infrastructure sentence, plat not submitted. The applicant lines there are Pigeon-Ardurra LLC and Ardurra Group on behalf of Crystal Ridge Property Group, LLC, inside CPA/AA/PUD-22-01.

Crystal Ridge may start roads and ponds. Town Center is the file the county already calls under construction. Crystal Ridge has no final-plat number on the August 18 list. Town Center has FPLT2025-00003, still in revisions. One is residential and earlier on the plat clock. One is nonresidential and later on the construction clock. Both are Lecanto. Neither is a sold street, and neither county sentence prints a builder, an HOA fee, a CDD, or a price.

A buyer being walked through a dirt field on Crystal Oaks Drive is in a different conversation from a user being walked along a curb on CR-486. Ask which file number is on the paper. If the number is IMP2024-00005 or IMP2024-00006, you are in the residential PUD and the plat has not been submitted. If the number is IMP2024-00001, you are in the commercial subdivision that is under construction, and the plat is in revisions. If the number is FPLT2026-00005, you are at Corta, seven lots, mylar still out.

The highway this site sits on

Town Center’s address is West Norvell Bryant Highway, which is CR-486. Florida’s Turnpike Enterprise’s project page for the Suncoast Parkway / SR 589 extension says the enterprise is extending the road 5.5 miles from W. Norvell Bryant Highway / CR-486 to CR-495. That segment is Phase 3A of Suncoast Parkway 2, a four-lane tolled roadway, two lanes in each direction. The same page estimates the project at $195 million and says construction is expected to continue through mid-2030. That is a Turnpike construction file for the highway. It is not a Citrus County plat for 3499, and it does not put Town Center inside the right-of-way.

The county’s own interchange file is separate again. CPA-2025-00008, prepared by Wade Trim as a consultant for Citrus County, proposes an interchange management area and comprehensive-plan standards for a CR-486 Interchange Management Area. On the August 18 list: Planning and Development Commission approval May 7, 2026; Board of County Commissioners transmittal June 22, 2026, at 5:01 p.m.; adoption hearing set for October 26, 2026, at 5:01 p.m. An adoption hearing is a plan clock. It is not a yes-vote, and it is not IMP2024-00001. The October 26 file gets its own reading when the board meets. This page only needs the date so a pad conversation does not pretend the map is already adopted.

The official design meeting for the parkway segment that starts at this highway is below. It is Florida’s Turnpike Enterprise’s virtual public information meeting for Suncoast Parkway 2, Phase 3, from CR-486 to US-19, held March 7, 2023. It is a corridor archive. It is not a Black Diamond Town Center advertisement, and it is not a claim that these commercial lots were drawn in that meeting.

Official Florida’s Turnpike Enterprise / FDOT design public information meeting for Suncoast Parkway 2 Phase 3 (CR-486 to US-19). Corridor archive, not a subdivision advertisement.

Use the video for the alignment story the Turnpike told the public. Phase 3 on that recording runs from CR-486 to US-19 and is split at CR-495. Use the August 18 applications list for Town Center’s construction status. Use the current Turnpike project page for the 5.5 miles, the $195 million estimate, and the mid-2030 construction window. A 2023 design meeting and a 2026 project page are different vintages. Do not treat either one as a recorded plat.

People, schools, and a commercial pad

The population briefing is the people tape for this map. Census QuickFacts, vintage V2025, puts Citrus at 171,666 on July 1, 2025. The Bureau of Economic and Business Research’s April 1, 2025 official estimate is 166,500, of which 155,292 were unincorporated. Crystal River’s April 1 count was 3,271. The school district’s January 27, 2025 preliminary projection was 14,845 students. QuickFacts lists 38.1 percent of residents as age 65 and over and 14.2 percent under 18. Household size is 2.24. The 2020–2024 owner-occupied share is 85.2 percent. Housing units: 90,919. The housing-value figure on that QuickFacts table is the ACS 2020–2024 median owner-occupied value, $245,500. That is a house value. It is not a commercial pad price, and this page does not turn it into one.

An older, owner-heavy, unincorporated county is a grocery, medical, and services county more than a school-driven retail county. A nonresidential subdivision on CR-486 can add lots to the commercial map those households already use. It does not rewrite the school file, and it does not create a Citrus absorption rate. Citrus 2050, the comprehensive-plan update on citruscounty.gov, is the plan being rewritten against that mix. The current operating plan is still the 2030 plan. An open plat on Norvell Bryant is not Citrus 2050. The rewrite runs from fall 2025 through winter 2027. An open house is set for October 19, 2026, 5:30–7:30 p.m., at the Lecanto Government Building. Showing up that night does not record FPLT2025-00003.

What this tape is not

It is not the Black Diamond Ranch home guide, not a builder, not an owner beyond the applicant line the county printed, not an HOA, a CDD, a rent, a cap rate, or a list price. Those figures are not on the August 18 applications page. It is not Crystal Ridge’s unplatted residential phases, not Corta’s seven-lot mylar, and not the review files still waiting on Norvell Bryant. It is also not the 6.95% Freddie Mac survey, not the September 16 FOMC hike, and not the August starts print. Those national tapes change the payment and the credit backdrop. They do not record FPLT2025-00003.

What it does to commercial real estate

For a user who wants a bay on CR-486, Town Center is a subdivision under construction with an open plat, not a space you can tour from a rent roll the county published. Ask whether the lot exists on a recorded map. On August 18 it does not. Ask who the applicant is: Pigeon-Ardurra LLC. Then ask the questions the page does not answer: who will own the lot after recording, what a building permit will allow, and what the occupancy will cost. Lease versus buy is the occupancy file. The Citrus commercial overview and the Lecanto corridor guide are the market files. Bridge Point’s commercial buying page is the service layer when the question is a specific site.

For a land buyer, under construction is evidence the civil work has a county status, not an asking price. Citrus commercial land is the land file. Entitlement, access, utilities, and flood still decide value. The plat revisions are the paper that turns infrastructure into a deedable lot. A mylar next door at 3503 is a different file. Do not price 3499 off Corta’s seven lots, and do not borrow the 230,000 square feet from the SN Lecanto 486 proposal to describe this one.

For a lender or a developer reading national credit next to local dirt, the July SLOOS briefing said banks eased standards on nonfarm nonresidential and multifamily loans in the second quarter, while construction and land-development demand weakened. The H.8 commercial real estate book was $3.13 trillion in early September. Census and the county count plans and statuses. SLOOS asks whether the dirt loan still gets done. A Citrus subdivision already under construction is local evidence of one file that cleared an improvement plan. It is not evidence that every CR-486 proposal has a construction loan. The five-acre medical office at 4290 is still in sufficiency review. The Citrus medical guide is the healthcare file. Damron’s office proposal is not a hospital, and it is not under construction on this list.

Last week’s 6.95% survey is a house-rate tape: 30-year at 6.95% and 15-year at 6.26% for the week ending September 17. The September 16 hike set the funds rate at 3.75–4.00% on a 12–0 vote. Commercial coupons are not that survey. A user who borrows against a house to occupy a small building still feels the house rate. A construction loan feels the credit tape. Neither coupon is printed on IMP2024-00001. A house payment still starts with a written quote on the mortgage page.

What it does to housing nearby

Town Center does not add a house. It adds commercial construction on the highway Lecanto already uses for daily errands. A resale buyer on a street that feeds CR-486 should treat the construction sentence as a disclosure item: work is underway at 3499, the plat is still open, and the interchange-area plan is set for an October 26 adoption hearing. That can mean traffic, noise, and a changing frontage. It is not an automatic raise, and it is not an automatic cut. Price the house against current comps on the same street type. The pricing guide is the process. The QuickFacts owner-value of $245,500 is a countywide ACS figure, not a Lecanto list price.

Nearby residential paper is not this subdivision. Amber Ridge’s 129 lots and Sola Vista’s 8 lots are review files on the same highway. Crystal Ridge’s 234 plus about 213 proposed lots can start infrastructure inland, and those plats are not in. Citrus Hills, Beverly Hills, Pine Ridge, and Citrus Springs remain existing street files. Do not shop a 1990s ranch as if Town Center had delivered a grocery and Crystal Ridge had delivered several hundred closings.

Insurance and flood stay separate from the plat. An improvement plan does not reprice an HO-3 policy. The flood and insurance guide is the paperwork logic, including for a Citrus house. A pre-approval from July is still a credit story. If a Florida Housing second mortgage is in a house stack, use the Hometown Heroes briefing. That program is a house product. It does not apply to a commercial lot.

How to use this briefing on a specific site

Print the vintage. If you are talking to a lender, an appraiser, or a seller, use the county’s own labels: Citrus County development applications, updated August 18, 2026; Black Diamond Town Center; IMP2024-00001; 3499 W Norvell Bryant Highway, Lecanto; approval issued; subdivision under construction; final plat FPLT2025-00003 awaiting applicant revisions. Do not say Black Diamond is leasing.

Put the plat sentence in the same paragraph as the construction sentence. Construction without an open plat is a finished subdivision. An open plat without the construction sentence is a different file — Corta, or Crystal Ridge, or a review case.

Keep four names in four sentences. Black Diamond Town Center is the CR-486 nonresidential subdivision under construction. Corta Black Diamond is seven nonresidential lots and one tract at 3503, awaiting a mylar. Black Diamond Ranch is the golf community with its own home guide. Crystal Ridge is the inland residential planned unit development that may start infrastructure and has no plat number yet.

Price a house against comps and a current written quote. Price a commercial lot against the recorded map when it exists, the access, and a loan a bank will actually make. The rate tape is 6.95% for a 30-year house loan as of the September 17 Freddie Mac survey. The policy tape is 3.75–4.00%. The ACS owner-value is $245,500. None of those three is a Town Center rent or a pad price, because the county page does not print one. Statewide context stays on the Florida markets page.

The through-line

Black Diamond Town Center is the Citrus commercial subdivision the county’s August 18, 2026 list already places in the ground. IMP2024-00001 at 3499 W Norvell Bryant Hwy is approved, and the subdivision is under construction. FPLT2025-00003 is submitted and still awaiting the applicant’s revisions. The county did not print a lot count, a square footage, a builder, a rent, or a price. The file next door has seven lots and a mylar still out. The large square-footage proposals on the same highway are still in review. The people tape next to that dirt is unincorporated, older, and not a school boom. The house-rate tape is 6.95%. The national construction tape is starts at 1.275 million and completions down 11.9 percent. If you are buying a pad, listing a nearby house, or underwriting a user on CR-486 this fall, use the county status, the open plat, and the building that actually exists.

Bridge Point’s commercial buying and investment pages, and the residential buying and home selling pages, are the service layer when you want that read against a specific address.

What to watch next

  • Citrus applications list: the next staff update after August 18, 2026. Watch whether FPLT2025-00003 moves from awaiting revisions to a recorded plat, and whether Corta’s mylar, FPLT2026-00005, records.
  • CR-486 Interchange Management Area (CPA-2025-00008): adoption hearing October 26, 2026, 5:01 p.m. A hearing date is not an adopted map.
  • Mythri Lecanto: tentative Planning and Development Commission date November 12, 2026. Tentative is not approved.
  • August new-home sales, national: Census and HUD, September 24. A separate sales tape. It will not print a Citrus commercial absorption figure.
  • Next Freddie Mac survey: September 24. A house-rate print, not a pad quote.
  • Minutes of the September 15–16 FOMC meeting: October 7.

Sources: Citrus County Board of County Commissioners, Development Applications Submitted, page updated August 18, 2026 — Black Diamond Town Center IMP2024-00001 (Pigeon-Ardurra LLC; nonresidential lots and infrastructure; 3499 W Norvell Bryant Hwy, Lecanto; approval issued; subdivision under construction; final plat FPLT2025-00003 awaiting applicant revisions); Corta Black Diamond FPLT2026-00005 (seven non-residential lots and one tract; 3503 W Norvell Bryant Hwy; staff recommendation; awaiting final mylar); Amber Ridge Phase 1 IMP2026-00002; Sola Vista Villas IMP2026-00003; Mythri Lecanto CPA/AA/PUD-2025-00009; SN Lecanto 486 CPA/AA-PUD-2026-00003; Damron CPA/AA/PUD-2026-00004; YMCA permits BLD2606-1325 and BLD2606-0765; Crystal Ridge IMP2024-00005 and IMP2024-00006; Southern Woods Phase V IMP2023-00005; Hills of Lecanto IMP2026-00006; Post Oak Ranch CPA/AA-PUD-2026-00005; River Oaks PUD-2026-00002; CPA-2025-00008 CR-486 Interchange Management Area (Planning and Development Commission May 7, 2026 approval; Board transmittal June 22, 2026, 5:01 p.m.; adoption set October 26, 2026, 5:01 p.m.). Citrus County, Non-Residential Development. Florida’s Turnpike Enterprise, Suncoast Parkway / SR 589 extension project page (Phase 3A, 5.5 miles from CR-486 to CR-495; estimated $195 million; construction expected through mid-2030) and the March 7, 2023 virtual public information meeting for Suncoast Parkway 2 Phase 3, CR-486 to US-19. Census QuickFacts Citrus County (V2025), BEBR / Florida Demographic Estimating Conference April 1, 2025 estimates, and Citrus County Schools’ January 27, 2025 projection, cited as the already-published people tape. Freddie Mac Primary Mortgage Market Survey (September 17, 2026), FOMC statement (September 16, 2026), Census/HUD CB26-147, and the July 2026 SLOOS cited only as separate national tapes.

For help reading this against a specific house, pad, or user requirement in Citrus County — or against Hernando, Pasco, Hillsborough, or Pinellas — contact Bridge Point Business & Real Estate Advisors at 352-515-0226 or request a consultation.

Questions people ask first

Quick answers to common questions about this topic.

What is Black Diamond Town Center?+

It is a nonresidential subdivision on Citrus County’s development-applications list. Improvement plans IMP2024-00001, filed by Pigeon-Ardurra LLC, cover nonresidential lots and infrastructure at 3499 W Norvell Bryant Highway (CR-486) in Lecanto. On the August 18, 2026 update, approval has been issued and the subdivision is under construction.

Is Black Diamond Town Center the same as Black Diamond Ranch?+

No. Black Diamond Ranch is an existing Lecanto golf community with its own home guide. Town Center is a CR-486 commercial subdivision. Corta Black Diamond, at 3503 W Norvell Bryant Highway, is a separate seven-lot nonresidential plat. Crystal Ridge is a separate inland residential planned unit development.

Has the Town Center plat been recorded?+

Not on the August 18, 2026 county list. Final plat FPLT2025-00003 has been submitted and is awaiting revisions from the applicant. The subdivision can be under construction while the map that creates deedable lots is still open.

How many lots or how many square feet are in Town Center?+

The county page does not say. It says nonresidential lots and infrastructure. It does not print a lot count or a square footage. Corta Black Diamond, next door, does print a count: seven non-residential lots and one tract. Do not borrow that count, or anyone else’s square footage, for 3499.

Who is the builder or the owner?+

The August 18 list names the applicant, Pigeon-Ardurra LLC. It does not name a production builder, a landlord, an HOA, or a CDD, and it does not say the applicant is acting on behalf of a client. There is no rent, cap rate, or list price on that line.

What else on CR-486 is actually under construction?+

On that applications page, Town Center is the subdivision the county says is under construction. Amber Ridge, Sola Vista, Mythri Lecanto, SN Lecanto 486, and the Damron office proposal are review or sufficiency files. The YMCA permits are for pickleball courts and a 5,000-square-foot addition on an existing campus, not this subdivision.

How is this different from Crystal Ridge?+

Crystal Ridge Phase 1 and Phase 2A are residential files the county cleared so infrastructure can commence. Neither final plat has been submitted. Town Center is nonresidential, the county says it is under construction, and a final plat number already exists and is in revisions.

Does the Suncoast Parkway project include this subdivision?+

No. Florida’s Turnpike Enterprise is extending SR 589 about 5.5 miles from CR-486 to CR-495, estimated at $195 million, with construction expected through mid-2030. That is the highway file. Town Center is a county subdivision plat at 3499 W Norvell Bryant Highway. The October 26, 2026 adoption hearing for the CR-486 Interchange Management Area is a comprehensive-plan clock, not this improvement plan.

Does this change Citrus home prices or school enrollment?+

The applications page does not print a price, and a commercial subdivision is not a classroom count. Census QuickFacts puts the county at 171,666 people. The school district’s preliminary 2025–26 projection was 14,845 students. The ACS owner-occupied value on QuickFacts is $245,500, which is a house figure, not a pad price.

What should I watch next?+

The next update of the county applications page, for a recorded FPLT2025-00003 or a recorded Corta mylar. The CR-486 Interchange Management Area adoption hearing is set for October 26, 2026, at 5:01 p.m. August new-home sales, on September 24, is a national housing tape and will not print a Citrus commercial absorption figure.

Who can help apply this file to a specific Lecanto property?+

Bridge Point Business & Real Estate Advisors advises buyers and sellers across Citrus, Hernando, Pasco, Hillsborough, and Pinellas. Call 352-515-0226 or request a consultation.

Talk with Bridge Point

Considering a purchase or sale in this market? Local guidance can make a meaningful difference.

Schedule a consultation

More articles

Representational late-morning photograph of a scraped inland Florida sandy lot with silt fence and leftover pines — not a listed property

Market Update · 17 min read

Crystal Ridge Can Start Dirt. The Plat Is Not Filed.

Citrus County’s August 18, 2026 applications list cleared Crystal Ridge Phase 1 (234 lots) and Phase 2A (about 213 lots) so infrastructure can commence. Neither final plat has been submitted. This is a start-of-build tape, not a sold street.

Representational late-morning photograph of a Nature Coast spring-fed creek through unincorporated marsh and cabbage palms — not a listed property

Market Update · 19 min read

Citrus Added People. The School Count Did Not.

Census QuickFacts puts Citrus County at 171,666 people. BEBR’s April 1, 2025 estimate is 166,500. The school district projected 14,845 students for 2025–26. The plan being rewritten is Citrus 2050.

Bridge Point Business & Real Estate Advisors

Real Estate Decisions. Better Advised.

Quick links

  • Commercial
  • Residential
  • Appraisals
  • Mortgage
  • Insights
  • About
  • Contact

Resources

  • Florida markets
  • Communities
  • Market reports
  • Property Management
  • Business Brokerage
  • Title

Connect

352-515-0226

info@BridgePointBREA.com

5467 Spring Hill Dr, Spring Hill, FL 34606

Stay informed

Get market updates and opportunities.

© 2026 Bridge Point Business & Real Estate Advisors. All rights reserved.

PrivacyTermsSitemap